Integrate Capacity Planning into the Budget

The single most fundamental flaw in the typical corporate budget is the failure to closely link capacity planning into the revenue and expense assumptions.  For example, a company forecasts significant changes in revenue, but not enough additional sales staff to bring in the new sales. Even if it does forecast a sufficient number of sales personnel, it assumes that each one will be fully effective as of the first day of work.  The inevitable result is only a slight increase in sales, if any.  The same problem can arise in many areas of the budget. Other common problem areas are:

There are several ways to mitigate these problems.  At the simplest level, itemize the key bottleneck areas, and conduct a manual review of the budget to ensure that there is sufficient capacity planned for each bottleneck.

A better approach is to build a capacity planning page into the budget model that highlights key problem areas. The following table shows a highly simplified capacity planning page for sales staff:

 
Quarter 1
Quarter 2
Quarter 3
Quarter 4
Budgeted revenue
$8,000,000
$10,000,000
$12,000,000
$14,000,000
Budgeted sales staff
27
32
38
42
Budgeted sales per person
$296,000
$313,000
$316,000
$333,000
Historical sales/salesperson
$250,000
$250,000
$250,000
$250,000

The table reveals a budget that is not likely to be achieved, since the new sales staff are expected to exceed the historical rate of sales.  In reality, the sales per salesperson should decline for some time, until the new sales staff can ramp up their contacts and product knowledge.

Another example appears in the next table, where a company appears to be adequately ramping up its consulting staff to meet planned revenue levels, but its assumed utilization percentage is unrealistic:

Quarter 1
Quarter 2
Quarter 3
Quarter 4
Budgeted consulting revenue
$2,106,000
$2,268,000
$2,565,000
$2,888,000
Budgeted consulting staff
52
56
60
64
Budgeted billing rate/person
$90
$90
$90
$95
Budgeted utilization percentage
90%
90%
95%
95%
Historical billing rate/person
$87
$87
$87
$90
Historical utilization percentage
82%
80%
84%
73%

In this case, the budget not only assumes far too high a utilization rate in all quarters, but especially in the fourth quarter, when the staff has traditionally taken time off for the holidays.

The examples shown here are simplistic, but can be used to highlight problems with the budget model. Building an adequate amount of ramp-up time or learning curve into the budget is much more difficult to verify through automation, and instead is best checked through a careful manual analysis of the model's underlying assumptions.